RNPP supplies 350MW to national grid on trial basis

Update : 17 Nov 2026, 18:01

The first unit of Rooppur Nuclear Power Plant on Tuesday began supplying 350 megawatts (MW) of electricity to the national grid on a trial basis, marking a milestone in Bangladesh’s first nuclear power project. 

The power supply began at 3:15pm in the presence of Science and Technology Minister Faqir Mahbub Anam, according to a press release of the Power Division.

The Power Division said the grid connection followed a long wait, continuous technical work and a series of complex tests at different stages of the project.

Under the initial trial plan, the generated electricity will be supplied to the national grid for around 8-10 hours.

During this period, engineers will conduct important technical tests to assess the performance and stability of the plant's turbine, generator and integrated grid operation system.

The plant will then be disconnected from the national grid for further technical tests. After a break of around 28 hours, it will again be connected to the grid for 4-6 hours to complete necessary technical and operational tests.

Dr Khalequzzaman, deputy project director of the Rooppur Nuclear Power Plant project, said electricity was supplied to the national grid on Tuesday afternoon as part of the grid synchronisation test.

However, the success of the process would depend on the results of various tests conducted earlier, he added.

Sources said the performance of different systems, including the turbine and generator, as well as their coordination with the national grid, would be closely examined at every stage.

If the test results are satisfactory and all scheduled activities are completed, approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) will be required for the next phase of trial operation.

Subject to regulatory approval, the plant will again be connected to the national grid on a trial basis to proceed with the next stage of electricity supply.

Under the agreement with the Russian contractor, the first unit will undergo a 10-month trial operation before beginning commercial electricity supply at full capacity.

Following the successful completion of the process, the first unit will be provisionally handed over by the Russian contractor to the Bangladesh Atomic Energy Commission.

Subsequently, the Nuclear Power Plant Company Bangladesh Limited (NPCBL) will begin operating as the designated operating organisation following a government gazette notification.

The Rooppur Nuclear Power Plant has two units, each with a generation capacity of 1,200MW, taking its total capacity to 2,400MW.

The project is expected to play an important role in meeting the country's growing electricity demand, ensuring energy security and supporting sustainable power generation.